  4. Construction of Box Culvert (2-Barrels)



  Project Cost : Php 864,429.91
  Source of Fund : 20% LGDF
  Location : Brgy. Tinagaan, Salay, Misamis Oriental
  Accomplishment : 82.81% as of December 11, 2019
  5.Construction of Multi-purpose Building (CICL & VAWC)



  Project Cost : Php 1,779,791.49
  Source of Fund : 20% LGDF & Trust Fund
  Location : Mun. Compound, Salay, Misamis Oriental
  Accomplishment : 84.66% (as of November 26, 2019)
  6.Concreting of Salagsag FMR


  Project Cost : Php 999,850.36
  Source of Fund : 20% LGDF
  Location : Brgy. Matampa, Salay, Misamis Oriental
  Accomplishment : 50% (as of December 27, 2019)
  7. Construction of Multi-purpose Building (H.E. & TESDA)


  Project Cost : Php 1,181,608.85
  Source of Fund : 20% LGDF
  Location : SCC Compound, Salay, Misamis Oriental
  Accomplishment : 85.97% (as of October 30, 2019)
  8. Construction of MPB (Senior Citizen Bldg.)



  Project Cost : Php 818,209.24
  Source of Fund : 20% LGDF
  Location : Salay river-2, Salay, Misamis Oriental
  Accomplishment : 67.77% as of October 11, 2019