PROJECT NAME  : CONSTRUCTION OF 3-STOREY (8-CL WITH OFFICES) SCHOOL BUILDING #1
  LOCATION    :  Salay Community College, Salay Misamis Oriental
  PROJECT COST   :  Php 18,992,852.74
  SOURCE OF FUND   :  DBP
  DATE STARTED   :  November 19, 2021
  TARGET DATE OF COMPLETION  :  July 17, 2022
  PROJECT STATUS  :  Ongoing
   CONTRACTOR    :  GLAXON Construction Services
  TARGET ACCOMPLISHMENT  :  46.88%
  ACTUAL ACCOMPLISHMENT  :  43.40%
  SLIPPAGE  :  -3.28%