PROGRAM AND PROJECTS
   A. Completed Projects Implemented by Contract
  1. Rehabilitation of Local Access Road



  Contract Cost : Php 7,408,861,96
  Location : Brgy. Alipuaton, Salay, Mis. Or.
  Contractor : VINNEX Enterprises
  Date Started : August 11, 2018
  Target Date of Completion:April 2, 2019
  Completed: March 29, 2019
  2. Improvement of WWS Level III



  Contract Cost : Php 24,926,838.72
  Source of Fund : OPPAP-PAMANA
  Contractor : AT Builders & Gen. Mdse
  Date Started : December 29, 2017
  Target Date of Completion : January 8, 2019
  Completed : August 12, 2019
  3. Expansion of WWS Level III (Design & Build)



  Contract Cost : Php 29,699,505.35
  Source of Fund : MDFO (Loan)
  Contractor : JTA Builders
  Date Started : January 20, 2017
  Target Date of Completion : June 21, 2018
  Completed :100%
  4. Construction of Perimeter Fence with Drainage Canal



  Contract Cost : Php 1,664,798.88
  Source of Fund : 20% LGDF
  Contractor : AT Builders and Gen. Mdse.
  Date Started : April 5, 2018
  Target Date of Completion : February 17,2019
  Completed : March 29, 2019
  B.Carry-Over Projects Implemented by Contract
  1. Construction of Seawall with Carriageway and Ecotourism Facilities (Phase-1)



  Contract Cost : Php 29,479,466.08
  Source of Fund : MDFO(Loan)
  Contractor : AT Builders & Gen. Mdse.
  Date Started : July 22, 2018
  Target Date of Completion : October 25, 2019
  Target Accomplishment : 42.17%
  Actual Accomplishment : 45.25%
Next Page >>